Can I install a renewable energy system if there is no hosting capacity available?

For towns where hosting capacity is unavailable, Horizon Power may consider a renewable energy system with Extended Ramp Rate Smoothing and Feed-In-Management.

For all system sizes (including connections up to 30kW) the assessment will be as per the LV EG Connection Technical Requirements. We will conduct a System Impact Study (SIS) which may identify the need for network augmentation, however, Horizon Power cannot confirm what these augmentation costs are until after the study is completed.

Fees and charges

  • Feed-in Management (FIM) charge: $14,000 
  • System Impact Study (SIS) for connections in towns without hosting capacity: Quote to be provided by Horizon Power on a case by case basis

How to apply
Please refer to our Technical Requirements for more information. To request an application form, please email renewables@horizonpower.com.au 

All prices are correct as at 1 July 2020, include GST and are subject to change at any time.

Let us know if you need any further assistance.

Fill in the form below or view our contact details to get in touch.

* Indicates a mandatory field.

Get in touch

Residential Account Enquiries:
1800 267 926
(8 am - 5 pm weekdays)

Business Account Enquiries:
1800 737 036
(8 am - 5 pm weekdays)

View all contact details